¡ØThere are guiding principles for safety and regulations for preventin
accidents Which we should obey in installation and operation of
GT-2031-5 as follows.
Inprinciple,
the ground concrete work should be executed by the client in accoredance
with teh drawings provided by Winner Technology Co., Ltd. and also
it can be carried out construction work by Winner Technology according
to the client's request with a separate expense.
The
distance between the end of barrier gate arm and the nearest building
should be over 500m at the least.
The
client should lock the housing without fail after finishing the
test operations of all the barrier gates for behicle.
Tht
installer should watch the operation of opening and closing by all
means during the test operation. It is prohibited to attach and
other operative element to invisible spot. The field of vision between
the barrier gate and the remote control system should be secured.
No other
person and obhect are allowed to be within the swing scope of the
barrier gate arm while the barrier gate is being operated.
If the length of barrier gate arm is more than 3.5m, an extra support
post should be installed at the ending point of the barrier gate.

The fizing of barrier gate should be firm enough to endure the wind
force of maximum 10(500N/§³) in front.
Power Supply and Wiring
After having been finished installation of the
system, power supply and wiring are carried out according to the
description provided along with the product. The controller for
barrier gate of Winner Technology may need a special wiring according
to using method and purpose.
And this can be supplied by Winner Technology, if needed.
|